Design Element
Project Background
Alliance
The Budget
>
Design Element

DEVELOPING THE BUDGET

Developing the budget for the project, or the Total Outturn Cost (TOC), is a complex process that depends on a large number of considerations. During the development of the TOC, the Alliance had to consider:

  • the spillway design that would deliver optimal water supply, flood mitigation, and dam safety
  • temporary inundation of land
  • community and stakeholder engagement
  • statutory approvals including the Significant Project application and project referral under the Environmental Protection and Biodiversity Conservation Act
  • liaison with Department of Natural Resources & Water ? Resource Operations Plan, water harvesting, South East Queensland Regional Water Supply Strategy
  • funding/subsidy management
  • compensatory habitat strategy
  • recreation area (amenity plan) & other facilities relocation

During the TOC development phase it was discovered that as a result of geological conditions on the right-hand side of the dam, additional works would be necessary to complete the project. As a result the development of the budget was divided into two parts: TOC 1 and TOC 2. TOC 1 would include the cost of raising the dam wall, reconfiguring the spillway and chute, recreational planning and development. TOC 2 would include the development and construction of a design solution to meet the geological challenges on the right hand side of the dam. TOC 1 was approved by GCCC on 4 June 2007. TOC2 was approved by GCCC in November 2007.
 



© 2007-2009 Hinze Dam Alliance, All Right Reserved
Footer Reflection
Design Element